DeVilliers Street Revitalization

Devilliers Streetscape Wider Concept - Close Up

project overview

The DeVilliers Street Revitalization Project includes streetscape and multi-modal improvements along DeVilliers Street from Cervantes Street to Main Street.  

Project features:

  • Sidewalks with decorative elements 
  • ADA enhancements
  • Curb-cut improvements
  • Lighting
  • Street trees & landscape
  • Crosswalks
  • Traffic calming elements
  • Bicycle safety improvements

Phasing:

  • Phase I includes the segment of DeVilliers from Main to Garden. 
  • Phase II includes the segment of DeVilliers from Garden to Cervantes.

project details:

  • CRA District: Urban Core
  • Est. Cost: $3.0 M

Design Plans and Concepts:





PROJECT STATUS

Phase 1: 

Construction 

Phase 2:

Pre-Construction (CST est. October 2020)

-----------------------------------------------

PROJECT UPDATES

To sign up for updates on this and other CRA projects, register for email or text alerts at City of Pensacola.com/Notify Me and select "CRA Projects".

------------------------------------------------

CONSTRUCTION SCHEDULE

Phase 1:

  • Commencement: August 2020
  • Est. Completion: Early 2021
  •  Typical Work Hours: Mon - Fri during daylight hours

Phase 2:

  •  Est. Commencement: October 2020
  •  Est. Completion: Mid 2021
  •  Typical Work Hours: TBD

------------------------------------------------

PAST EVENTS:


  •  June 5, 2019 - An open house concerning the A, DeVilliers    and Reus Streetscape plans was held.
  •  April 19, 2019 - 30-day comment period closed.
  •  March 19, 2019 - A public workshop concerning the A,     DeVilliers and Reus Streetscape plans was held.